Category: Project Reports

Vail Rotary Club Project

March 30,2016

ADEC beginning to install 10 chlorinators Tablets in the municipality of Yamaranguila, department of Intibuca.

pq_ DSC04813pq_ 20160315_114953

January 27,2016

Vail Rotary Club and ADEC are conducting a project that involves the installation of 30 chlorinators tablet in the departments of La Paz, Intibuca and Lempira, bacteriological tests and training to the Water Boards and communities for matters of disinfection of water, health and hygiene.

cloradores 2

Manufacturing Chlorinators Tablets for project

 

ADEC – Yamaranguila Municipality / Department of Intibuca

January 2015 –  Participated in the meeting of the Municipality of Yamaranguila where the report of all activities undertaken by ADEC in 2014 was given.  An additional 12 water boards were trained on issues of chlorination, operation and maintenance.

DSC02918DSC02905DSC02800DSC02806

No Comments

Categories: Circuit Rider Reports News

Progress Water Project El Cipres -La Paz / Rotary Global Grant GG1415095

On January 21, we visited the community again to see the progress made towards construction. A main storage tank has been completed and is nearly ready for water. Many lines have been installed and they are currently working on a suspended river crossing. The community is very excited for the completion of the project by the end of February.

IMG_20150121_125130IMG_20150121_132810 IMG_20150121_130848SAMSUNG CAMERA PICTURES

On December 3, all the necessary materials to build the water system (pipes, cement, bricks, etc.)were carried to community , the trench of conductión and distribution line has begun, tank is built by 50%.

1234Cipres167Cipres14Cipres12Cipres4Cipres221417319657323

 

On November 10, the Marcala Rotary Club and El Ciprés signed the agreement for execution of water project El Ciprés, where the entire community pledged to work to build their water system.
Besides meeting with the mayor of the municipality of Opatoro, the mayor agreed that the municipality will provide the sand and gravel. They already have the quotes for the materials and those will be purchased by the end of this week.
1235720141112_110718

 

 

 

No Comments

Categories: Current Projects News